Boris Bellesia
(Politecnico di Torino)
2/28/08, 9:00 AM
- What happens before powering tests after cooldown
- Main issues that slowed us down
- ELQA: Continue as for sector 45? Further optimisation of the strategy?
- What has been done during the powering tests? During what time? By whom? Efficiency?
- How to ensure minimization of re-commissioning 45 and to secure what has been achieved?
- How to avoid that changes during the “shutdown”...
Anne Funken
(CERN)
2/28/08, 9:30 AM
- Electrical safety during interventions, “consignation”
- Electrical safety subsectors
Magali Gruwe
(CERN)
2/28/08, 10:00 AM
- Hardware commissioning using the access system
- Set the rules for access, different modes
Mr
Hugues Thiesen, Dr
Karl Hubert Mess
(CERN AT-MEL)
2/28/08, 10:30 AM
- Tunnel access during powering – what can access during powering as a function of current in the different circuits? Clear and transparent rules.
Mr
Serge CLAUDET
(CERN AT ACR)
2/28/08, 11:10 AM
- Availability for cryogenic system
- Recovery time after quenches: what can we expect?
- Operation overnight and over the weekend: is it possible?
- Operation with several sectors in parallel, what will change?
- Presence in the CCC
- Level measurements
- How to ensure a correct Helium level for operation?
Dr
Andrzej SIEMKO
(CERN AT-MTM)
2/28/08, 11:40 AM
- What can be done at what temperature? (e.g. below 2.8 K low current tests), and when can we start the tests?
- Relaxed operation at reduced current (e.g. can we operate without cold compressors a magnet currents corresponding to 2 TeV)?
- Table for all steps and all circuits?
- Orbit correctors 60 / 120 A – what conditions? What needs to be watched by operators?
- Procedure: masking of...
David Nisbet
(CERN),
Yves Thurel
(CERN)
2/28/08, 12:10 PM
- 600 A spikes during 0 V crossing and QPS system
- Spikes and how to avoid them (IERROR and IEARTH)
- RB power converter performance, is there an issue?
Knud Dahlerup-Petersen
(CERN),
Reiner Denz
(CERN AT-MEL-PM)
2/28/08, 2:00 PM
- Partial heater firing if switches do not open – yes/no?
- Access to the tunnel for 600 A extraction switches, can be optimised?
- Firing heaters without current in the magnet circuit – Why? EMC due to other tests?
- Closing switches for many circuits
Antonio Vergara Fernandez
(Cent.de Investigac.Energeticas Medioambientales y Tecnol. (CIEMA)
2/28/08, 2:30 PM
- 450 GeV, 2 TeV and 5 .. 6 TeV: what circuits at what current? What can be left for later? (remember: it is always possible to bring in other circuits on the fly)
- How much time is required to commission for injection, for ~2 TeV, 4-6 TeV and 7 TeV? What could be gained? What circuits could be left out?
- When is tunnel access required? By whom? How to optimise it? What can be done...
Dr
Nuria Catalan Lasheras
(CERN),
Walter Venturini Delsolaro
(CERN)
2/28/08, 3:00 PM
- Procedures and their realisation in sequences: can they be lighter?
- EDMS approval of procedures and their changes
- Analysis and approval of test steps in CCC – can it be improved?
Arjan Verweij
(CERN),
Robert Henry Flora
(Fermi National Accelerator Lab. (Fermilab))
2/28/08, 3:30 PM
- What circuits?
- What quenches?
- Why did it quench?
Dr
Markus Zerlauth
(CERN)
2/28/08, 4:10 PM
- Status of PM system? Data gets sometimes stuck?
- PM event builder
- Can we become more efficient with more automatic analysis?
- Coherence MTF – LSA etc.
- Long tests: can one reduce the time of the test online, for example due to a long plateau? PASS TO THE NEXT STEP button.
- Managing powering: better SOC names to avoid confusion? SOCs per day?
- Tools for powering groups of...
Alvaro Marqueta Barbero
(Cent. Invest. Energ. Medioamb. Tec. (CIEMAT) - Consejo Sup. de I)
2/28/08, 4:40 PM
- How to improve the Powering Test Visualisation tool, etc.
- How to improve the planning tool (EXCEL?) Can both be merged?