- 450 GeV, 2 TeV and 5 .. 6 TeV: what circuits at what current? What can be left for later? (remember: it is always possible to bring in other circuits on the fly) - How much time is required to commission for injection, for ~2 TeV, 4-6 TeV and 7 TeV? What could be gained? What circuits could be left out? - When is tunnel access required? By whom? How to optimise it? What can be done without access to the tunnel?