This extended LTC meeting will address topics related to the commissioning of LHC with beam to an intermediate energy. Sessions will include cold check-out without beam and the readiness of the machine systems to operate with beam.
Friday 14 March
14:00 - Main Auditorium
Summing-up of meeting
- Achieve circulating beam as soon as we have a cold and minimally commissioned machine.
- Commission with beam to demonstrate that the machine is viable (captured beam and 1 hour lifetime).
- The first run for physics.
- The fall back solution:
- One or more sectors require a major repair and have to be warmed up.
- Sector test from one side or both on several healthy sectors while the repair is ongoing – access ? Or time sharing the week.
- The energy strategy.
- Schedule
Speaker:
Steve Myers
Slides
09:00
HWC– where are we?20m
The major non-conformities encountered, the ongoing work, repairs, etc. (PIMs, connection cryostats, coupling between bus-bars, water cooled cables and flexible connections, etc.). The planning for the coming months.
Speaker:
Roberto Saban
Slides
09:20
Overview of the commissioning of 4520m
- Where we come from (a recall of sector 78)
- What was achieved in sector 45: number of circuits, energy of the presently commissioned sector 45,
- how much more do we need for a reasonable energy level
Speaker:
Bellesia Boris
Slides
09:40
Issues arising from review and HW commissioning strategy over the coming months20m
o safety, access, resources (qps, interlocks, power converters, MPP, controls), availabilty of systems, etc
o Lessons from sector 4-5
o Parallelism between HWC and machine checkout (partial & full) – resources, expertise, limits
Speaker:
Rudiger Schmidt
Slides
10:00
--- Coffee break ---
30m
10:30
HW commissioning to intermediate energy35m
o How can we achieve a machine commissioned for beam operation for mid June?
o Objectives, advantages of HWC to intermediate energy.
o How much time can we gain?
o Can we achieve a commissioned machine for intermediate energy by mid-June? Critical issues for that?
o Is there a safe limit to operate the magnets and the cryogenics for cold check-out, early physics?
Speaker:
Antonio Vergara-Fernandez
Slides
11:05
Access System30m
o What is going to happen in the next 6 months?
o Present experience
o Closure of ring, preparation, qualification etc.
o Prerequisites, EIS…
o Access during a sector test
o Is the access system ready for HWC in parallel to a sectorized cold-check out in parallel to HWC and experiment preparation?
Speaker:
DrMagali Gruwe
Slides
11:35
Experiments during HWC, beam tests and initial commissioning30m
o What are the experiments going to do from March to the first collisions
o Can they leave with controlled access in the experimental areas in parallel with HWC and Cold-Check-out
o Impact of a Sector test
o How interested are the experiments in a run at intermediate energy?
Speaker:
Massimiliano Ferro-Luzzi
Slides
12:05
→
14:00
--- Lunch break ---
1h 55m
14:00
→
17:25
Session 2 - Preparation for Circulating Beam - Part I
14:00
Preparation for Beam commissioning35m
o Plans for preparation for beam commissioning, dry runs, system commissioning, machine protection commissioning, partial cold checkout, full machine check out.
Speaker:
Mike Lamont
Slides
14:35
Cryogenics towards operation35m
o How to operate up to 8 sectors together.
o Recovery after a quench: how much time does it take? Is expert intervention required? How can this be improved?
o Equipment folder: tests results, handling of non-conformities, performance below specs, machine as commissioned vs. machine as nominal
o Alarms/signals/SW available in CCC
o Piquet/Experts availability
Speaker:
Serge Claudet
Slides
15:10
Magnets & QPS towards operation35m
o How to operate up to 8 sectors together
o Recovery after a quench: how much time does it take? Is expert intervention required? How can this be improved?
o Equipment folder: tests results, handling of non-conformities, performance below specs, machine as commissioned vs. machine as nominal
o Alarms/signals/SW available in CCC
o Piquet/Experts availability
Speaker:
Nuria Catalan Lasheras
Slides
15:45
--- Coffee break ---
30m
16:15
Vacuum35m
o Breakdown of tests foreseen in preparation for beam
o Equipment folder: tests results, handling of non-conformities, performance below specs, machine as commissioned vs. machine as specified
o Issues for sectorized cold check-out in parallel to HWC
o Alarms/signals/SW available in CCC
o Piquet/experts availability
Speaker:
Jose Miguel jimenez
Slides
16:50
Injection/Beam Dump and Protection Devices35m
o Breakdown of tests foreseen in preparation for beam
o Equipment folder: tests results, handling of non-conformities, performance below specs, machine as commissioned vs. machine as specified
o Piquet/Experts availability
Session 2 - Preparation for Circulating Beam - Part II
08:30
RF35m
o Breakdown of tests foreseen in preparation for beam (including damper, synchronization signals and pre-pulses, RF instrumentation)
o Equipment folder: tests results, handling of non-conformities, performance below specs, machine as commissioned vs. machine as specified
o Piquet/Experts availability
Speaker:
Olivier Brunner
Slides
09:05
Beam Instrumentation40m
o Breakdown of tests foreseen in preparation for beam
o Equipment folder: tests results, handling of non-conformities, performance below specs, machine as commissioned vs. machine as specified
o Piquet/Experts availability
Speaker:
Jean-Jacques Gras
Slides
09:45
break
30m
10:15
Collimators35m
o Breakdown of tests foreseen in preparation for beam
o Equipment folder: tests results, handling of non-conformities, performance below specs, machine as commissioned vs. machine as specified
o Piquet/Experts availability
Speaker:
Oliver Aberle
Slides
10:50
Machine Interlocks35m
o Breakdown of the QA tests foreseen in preparation for beam
o Equipment folder: tests results, handling of non-conformities, performance below specs, machine as commissioned vs. machine as specified
o Piquet/Experts availability
Speaker:
Alick Macpherson
Slides
12:00
→
14:00
--- Lunch break ---
2h
14:00
→
17:30
Session 3 - Possible injection into part of the machine, preparation for beam
14:00
Options for possible sector test45m
- motivation
- options (injection point 8, injection point 2)
- prerequisites
- test outline, planned total intensities
Speaker:
Mike Lamont
Slides
14:45
Radiation Protection implications of possible sector test30m
- precautions before test, during test
- survey, zonage
- requirements after test
- tunnel, experiments
Speakers:
Doris Forkel-Wirth, DrHelmut Vincke
Slides
15:15
--- Coffee break ---
30m
15:45
Stopping the beam in a possible sector test30m
- point 7
- colimators, point 6
- beam dump
- point 3, point 4
- radiation levels
Speaker:
Stefano Redaelli
Slides
16:15
Proposed tests with beam45m
- run trough list,
- priorities,
- intensities
Speaker:
Massimo Giovannozzi
Slides
17:00
Quenches with beam30m
- Motivation
- Sector test, with circulating beam
- Method, dangers, intensities
- will HWC/MPP approve???
- Interference
Aperture model for the LHC. Summary of known aperture bottlenecks (e.g. Q2) and their documentation in the CCC. Procedures for the safe measurement of aperture in the LHC.
Speaker:
Stefano Redaelli
Slides
09:45
Beta beating, coupling, and dispersion35m
Procedures for measuring for verifying the optics in the LHC. Summary of correction algorithms and their implementation in LSA.
Speaker:
Rogelio Tomas Garcia
Abstract
Slides
10:20
--- Coffee break ---
30m
10:50
Orbit correction tools35m
Commissioning strategy for the orbit correction system (BPM errors; k-modulation). Options for feed back loop on orbit. Orbit correction in the LHC IR and collimation regions. Strategy for orbit threading.
Speaker:
Jorg Wenninger
Abstract
Slides
11:25
Tune and Chromaticity correction35m
Commissioning strategy for the tune and chromaticity correction systems. Options for feed back loop on tune and chromaticity.
Speaker:
Ralph Steinhagen
Slides
12:00
--- Lunch break ---
2h
14:00
Emittance35m
Procedures for measuring beam emittances in the LHC. Tools for minimizing emittance blow up during injection, ramp and squeeze. Procedures and tools for transfer line to LHC matching.
Speaker:
Frank Zimmermann
Abstract
Slides
14:35
Non-linear correction circuits35m
Procedures for adjusting the non-linear correction circuits in the LHC. Procedures for verifying the correction circuit settings
Speaker:
Massimo Giovannozzi
Abstract
Slides
15:10
--- Coffee break ---
30m
15:40
Verification of the Beam Loss studies at start-up35m
Procedures for calibrating loss patterns. Operational scenarios given measured BLM losses. Threshold adjustment and masking disabling during operation.
Speaker:
Laurette Ponce
Slides
16:15
MADX online model – Part 125m
Basic tasks and options. Implementation
Speaker:
Frank Schmidt
Slides
16:40
MADX online model – Part 225m
Integration into the LSA software and application of online MADX to operation
DB cluster introduction
New DB organization (LSA DB, Logging DB, Measurement DB, …)
Performance issues (all databases)
Logging DB: data rates – what is acceptable vs. what is expected
Speaker:
Chris Roderick
Slides
09:00
LSA Core30m
Introduction (scope, high level architecture)
Settings organisation for LHC
Transactions (FGCs, FESA)
Republication of information from LSA to DIP
Speaker:
Grzegorz Kruk
Slides
09:30
LSA & Safety30m
Introduction (motivation for RBAC and MCS)
What’s involved in making a property critical?
How we manage maintenance of RBAC roles and MCS definitions?
How do we ensure that configuration in LSA DB is in sync with Front-end?