Description
Presentation of the available protection mechanisms and discussion on the integration strategy of the EHBS card into the cryogenics control system. Consequences and advantages of automatic enabling the heater channels. Definition of the I/O error, Temporary (TS) and Full (FS) stops. Defining the cases when AC or DC mode can be used and the transitions between those modes.
Minutes
    • 10:35 10:50
      Specifications and available protection mechanisms of the Beam Screen Heater electronic card 15m
      Speaker: Nikolaos Trikoupis (CERN)
      Slides
    • 10:55 11:05
      Integration of the Electrical Heaters in the control system 10m
      Speaker: Dr Enrique Blanco Vinuela (CERN)
    • 11:05 12:00
      Discussion on the integration strategy for the EHBS: AC/DC modes of operation, automatic enabling, I/O error, temporary and full stops 55m
    • 11:30 11:45
      Discussion: Missing global test on Mirror bench (RadTol & FEC & PLC & PVSS) 15m
    • 11:45 11:55
      "Solution 1" - PLC: Beep logic 10m
      Speaker: Antonio Tovar-Gonzalez (CERN)
    • 11:55 12:05
      "Solution 1" - FEC : TS, FS & I/OError 10m
      Speaker: Dr Enrique Blanco Vinuela (CERN)
    • 12:05 12:15
      Discussion: Planning deployment of Solution 1 10m
    • 12:15 12:25
      Aspects of the EHBS design 10m
      Speaker: Nikolaos Trikoupis (CERN)
    • 12:25 12:35
      Discussion: "Solution 2" - Planning 10m