Help us make Indico better by taking this survey! Aidez-nous à améliorer Indico en répondant à ce sondage !

25–29 Sept 2006
Valencia, Spain
Europe/Zurich timezone

CMS Optical Links - Lessons learned from Mass Production

27 Sept 2006, 16:20
1h 40m
Valencia, Spain

Valencia, Spain

IFIC – Instituto de Fisica Corpuscular Edificio Institutos de Investgación Apartado de Correos 22085 E-46071 València SPAIN

Speaker

Jan Troska (CERN)

Description

The CMS Tracker will install over 40000 optical links in its data readout and control system, representing an unprecedented deployment of this technology in a Particle Physics Experiment. After reviewing the Quality process employed in this project, a summary of the performance data measured during production will be shown. The analysis of this data will then be used to illustrate how the performance of the installed system may be predicted, giving confidence that the specified functionality will be attained in the final system. Completion of the production has allowed reflection upon the processes used and improvements for future such projects will be given in the form of some lessons learned.

Summary

Production of components for the 40000 optical links of the data readout and control
system of the CMS Tracker is now complete. The Quality Assurance process put in
place for the production yielded detailed performance data for each individual
component produced. The QA process put in place before component-production started
will be outlined. For such an unprecedented (in the field of Particle Physics) scale
of production all components were produced by industrial partners. This was made
possible through the choice of COTS-based components with only minimal modification
to meet the criteria set by the CMS Tracker environment. Production proceeded in
batches, with the manufacturers providing per-device measurements of the key
performance parameters with delivery of the batch. Batch-level acceptance was then
carried out at CERN to verify these measurements.
The large number of components produced has yielded a unique data set of component
performance that can be used to make statistical predictions on the overall
performance of the links that will be installed in CMS. Analysis of this data will
be presented, showing on the one hand the progression of production from start to
finish and highlighting the issues that occurred along the way; and on the other hand
giving data that can be used to predict the performance margins of the installed
links. For the analogue readout system of the CMS Tracker the gain of the individual
links is of utmost importance, since it directly affects the overall dynamic range of
the full readout chain. It will be shown that the final performance dataset confirms
the prediction that all links will enable data to be transmitted with sufficient
margin. For the digital control system that is based upon the same components as the
analogue readout system these data allow the confirmation of the operating margins.
We will also reflect upon the progression of the production and the problems
encountered along the way. The most critical phase of the process for all components
was the start-up phase during which the manufacturing process was qualified by CERN.
It was in this phase that the largest number of issues had to be resolved so that
the production could then proceed smoothly to the end. We will conclude by providing
some lessons learned for future projects of this scale.

Primary author

Co-authors

Mr Daniel Ricci (INFN Perugia) Dr Francois Vasey (CERN) Dr Karl Gill (CERN) Mr Robert Grabit (CERN) Mr Stefanos Dris (CERN and Imperial College, London)

Presentation materials