LIU BWS Mechanics Production Readiness Review
LIU Wire Scanner Production Readiness Review
29 March 2017
INDICO: https://indico.cern.ch/event/618262/
Present:
-
Federico Roncarolo, Lars Jensen, Jose Sirvent, Malika Meddahi, Giovanni Rumolo, Jonathan Emery, Patrik Andersson, Jose Somoza, Benoit Salvant, Klaus Hanke, William Andreazza, Thibaut Lefevre, Dimitry Gudkov, Nicolas Chritin, Jocelyn Tan, Bettina Mikulec, Alessandro Dallocchio, Alexandre Mariet, Emilien Rigutto, Stephen Jackson, Christine Vollinger, Thomas Kaltenbacher
Scope (Ray):
Questions to be addressed in this review
-
Is the mechanical design satisfactory and ready to proceed for series production?
-
Do we have confidence that this instrument will fulfil the specification for LIU?
-
Do we have confidence that the instrument:
-
Will be qualified for vacuum acceptance?
-
Will not have a major impact on machine operation due to impedance?
-
Should not suffer wire breakage due to impedance heating?
-
-
Is the series budget and schedule understood and are the costs justified?
Mechanical Design (Dimitry)
New design to address issues/limitations with existing scanners:
-
Motion is transferred through crank mechanism
-
Bellows for motion transfer
-
Inaccuracies due to the relatively complex mechanics (crank-slider mechanism)
-
High deformation of forks during movement
-
Polymer materials used in mechanism design
-
Custom Helicoflex flange and seal
Initial SPS prototype needed to be improved in terms of:
-
Weight and size (wasn’t designed for the PSB)
-
Non-standard ConFlat flange (DN400)
-
Optical encoder components are inside the vacuum volume
-
Drum-based design, complicated and expensive for production
New design in close collaboration with IWG, TE-VSC, EN-MME
-
2 main components - vacuum tank & kinematic unit
-
Kinematic unit the same for all machines
-
Only fork size & position on shaft changes
-
-
4 variants of vacuum tank
-
H&V for SPB, PS & SPS
-
-
Geometry optimised for UHV - pumping holes included for all possible trapped volumes
-
Design approved by VSC
-
-
Reliability
-
SPS prototype tested to 75000 cycles with no degradation observed
-
Long term tests to over 100000 cycles foreseen for 2nd PSB prototype
-
Components
-
Stepped chamber - most complicated mechanical part to produce
-
Requires electron beam welding
-
-
Optical encoder
-
Glass disk currently used, but favoured solution is LESS Al disk
-
-
Forks
-
3D additive Ti manufacturing - tested for vacuum compatibility - OK from VSC
-
Status
-
SPS & PSB scanners installed
-
Integration
-
PSB H&V - underway with 3D drawings to be prepared
-
Looks to be interference between SEM grid on ring 3
-
ACTION: BI-ML to check integration of SEM grid & WS for PSB
-
-
PS & SPS - 3D integration complete
-
-
No - not compatible with final design.
-
Used to verify design which led to optimisation of
-
Weight & size - non-standard flange replaced
-
Motor & control
-
Drum based design - changed to cantilevered shaft
-
Optical components - moved out of vacuum
-
Mechanical Production (William)
Tanks - MS & IT required
-
Documents prepared & meeting with spec committee done
-
Aim - contract signed 3rd quarter 2017
-
Delivery 1st quarter 2018
Stepped chamber
-
Price enquiry for machining with EB welding at CERN
-
Delivery 1st quarter 2018
Mechanical components
-
Procurement handled by MME for ~2500 parts
-
Delivery 1st quarter 2018
Supports
-
Design ongoing, price enquiry MME
-
Delivery 3rd quarter 2018
Motor
-
Single tender (ALXIOM) with price request submitted
-
Delivery 4th quarter 2017
-
Instrument bakeable? - not required & not tested but design in principle was for bakeable instrument
-
Main worry for schedule - no critical item identified - aim to have all ready for start of LS2
-
VSC qualification comes last & can always give surprises & lead to delays. Try to test components and ensure cleanliness during assembly process – hence the need for the clean assembly area.
-
-
MME on-board - e.g. e-beam welding? Yes
Vacuum Acceptance (Jose)
Mechanical components - Individual tests - all OK
RGA of full system
-
Issues after cleaning/assembly required to repeat the process
-
Origin of contamination not fully understood
-
Cleaning and assembly of different components is critical
Co-axial Kapton cable
-
Identified as main outgassing item
-
Diffusion of water in very thin Kapton® layer
-
Bakeout with subsequent exposure to air does not help long term outgassing
-
Only helps when bakeout in situ
-
-
For PSB
-
FWS out of spec at 24h but in spec at >300h
-
Summary
-
Once exposed to air Kapton re-absorbs water so no improvement in pumpdown rate
-
With ion pump added even current Kapton cable OK for PSB & SPS
-
Not OK for PS
-
Need ion pump & change of wire
-
VSC recommendation to add ion pump & change of wire for PS
-
Retrofit cable on all scanners if suitable replacement found
Expected Performance (Federico)
Wire position determination
-
Old system
-
Rotational WS: Relies on calibration tables
-
Linear : direct use of potentiometer
-
-
New system
-
Beam size: inferred from angular position from optical disk - no calibration required
-
Beam positon (offset) : still requires calibration
-
Sources of uncertainty for beam size measurement
-
Wire position uncertainty
-
Optical disk
-
10urad precision and reproducibility
-
Translates to error < 1.5 um
-
-
Mechanical plays
-
Fork deformation
-
Wire vibration
-
-
Acquisition electronics
-
Detector
-
Acquisition
-
Fit routine
-
SPS Prototype Coasting Beam Results
-
270GeV with PMT down to 1.5 spread in measurements
-
12um sigma on ~800um beam size
-
Compared to 22um for linear scanner
-
-
400GeV pulsed with single bunch
-
12um on beam centroid
-
107nm! on beam size
-
ACTION:
-
BE-BI to provide a table summarising wire position uncertainty & calibration test bench results
Comments regarding results from calibrations:
Comments regarding scope for use in the SPS:
Impedance (Christine)
PSB - simulations & measurements:
-
Simulations compared to probe-probe measurements and probe-coupler measurements
-
2 strong modes simulated & measured at 812 MHz & 867 MHz
-
Well above beam spectrum
-
-
Effective impedance negligible
Simulations for SPS & PS:
-
Effective impedance also found to be negligible
Conclusion: no visible showstopper expected from transverse or longitudinal impedance
Wire heating
-
Highest induced power observed at 523 MHz and 882 MHz at 135 deg position
-
PSB expect no influence (above beam spectrum)
-
PS 0.01 W/turn from 874MHz mode at 0 degree (parking)
-
SPS
-
0.11 W/turn from 523 MHz mode at 0 degree (parking)
-
1.98 W/turn from both modes at 135 degree
-
Need to check units!!
-
-
-
Heating will depend on interaction with beam modes
-
With ferrites will always interact, i.e. heat
-
Without ferrites will depend on mode frequency
-
No ferrites therefore preferred as long as modes are not hit
-
ACTIONS:
-
Bench measurement with real wire (ACTION: Impedance WG with help from BI)
-
MD with high intensity in SPS
-
Possibility to instrument SPS prototype wire with higher frequency readout (ACTION: BE-BI in collaboration with Impedance WG)
-
Cost & Schedule (Ray)
Unit costs for production:
-
Material + vacuum tank & chambers + instrument + support
-
57 kCHF/ instrument
-
-
Control Electronics + Acquisition system
-
23.5 kCHF/ instrument
-
-
Cabling average
-
33.4 kCHF/ instrument
-
Budget:
-
1258 kCHF for series production
-
780kCHF for cabling, vac interface, remaining design
-
133kCHF for assembly & calibration benches
2.2MCHF TOTAL BUDGET for installed scanners
-
1.3MCHF remaining in EVM
-
0.9MCHF additional required
Spares - 280kCHF
Options - 308kCHF
Summary
Decision on go-ahead needed or mechanics early May for tendering to start mid-May
-
VSC OK
-
Impedance OK
-
Mechanical performance to be finalised
-
LIU needs input on final expected mechanical performance by end April
-
MAIN ACTIONS:
-
BE-BI to produce table of precision uncertainty for mechanical system and address the comments regarding calibration and scope for use in the SPS.
-
LIU management to see how additional costs can be covered in discussion with CONS
-
BE-BI to organise follow-up meeting end of April to present & discuss this table