LHC Collimation Review 2011
→
Europe/Zurich
CERN
CERN
Mike Seidel
(PSI),
Ralph Assmann
(CERN)
Description
The "phase 1" of LHC collimation has been fully commissioned, allowing a stored beam energy in the LHC of more than 80 MJ. Its performance has been characterized with beam at 3.5 TeV. This review is considering the present performance, possible limitations in future operation and plans for the upgrade of the system. In particular, it should be reviewed whether the upgrade work in the IR3 dispersion suppressors can be delayed by three years without limiting the LHC performance at 7 TeV.
Review Committee:
Mike Seidel (PSI, chair), Tiziano Camporesi (CERN), Wolfram Fischer (BNL), Brennan Goddard (CERN), Mike Lamont (CERN), Thomas Markiewicz (SLAC), Nikolai Mokhov (FNAL), Andrzej Siemko (CERN), Johannes Wessel (U. Muenster)
Charge:
Review collimation status and upgrade plans. Advise on the following questions:
Review Committee:
Mike Seidel (PSI, chair), Tiziano Camporesi (CERN), Wolfram Fischer (BNL), Brennan Goddard (CERN), Mike Lamont (CERN), Thomas Markiewicz (SLAC), Nikolai Mokhov (FNAL), Andrzej Siemko (CERN), Johannes Wessel (U. Muenster)
Charge:
Review collimation status and upgrade plans. Advise on the following questions:
- Are collimation performance and limitations properly analyzed and adequately addressed by upgrade plans?
- Can the collimation upgrade in the IR3 dispersion suppressors, presently foreseen for the 2013/4 shutdown, be delayed by three years without limiting LHC performance at 7 TeV?
- Have any issues or risks been overlooked that should be addressed in the collimation upgrade plan?
Contact
-
-
Executive session (closed) Salle Andersson
Salle Andersson
CERN
-
Presentations: Overview on collimation system and present results Salle Andersson
Salle Andersson
CERN
-
1
WelcomeSpeaker: Dr Ralph Wolfgang Assmann (CERN)
-
2
Introduction to LHC collimationCollimation system description: multi-stage cleaning, different planes, betatron and momentum. Definition of cleaning efficiency. Introduction quench limit. Hierarchy. Limiting physics processes: single-diffractive p scattering, ion fragmentation, ... Comments on hollow e-beam scrapers.Speaker: Dr Stefano Redaelli (CERN)
-
09:55
Discussion
-
3
Collimation setup and performanceHow is it adjusted? How does it perform in LHC (loss maps: measurement and simulation). MD results at 3.5TeV and performance reach at 7TeV. Losses in luminosity production (dispersion suppressors). Measurement protons vs ions. Minimum beam lifetime. First SPS results BPM’s in jaws.Speaker: Daniel Wollmann (CERN)
-
10:20
Discussion
-
10:25
Coffee Break
- 4
-
11:05
Discussion
-
5
Collimation margins and beta*Stability of LHC machine (orbit, beta). Required margins for collimation setup. Connection collimation to beta*. What beta* can be achieved? Origins of limitations: protection condition, infrequent collimation setups, machine drifts.Speaker: Roderik Bruce (CERN)
-
11:25
Discussion
- 6
-
11:45
Discussion
- 7
-
12:10
Discussion
- 8
-
12:25
Discussion
-
1
-
12:30
Lunch
-
Presentations: Motivation and plans for collimation upgrade (with ATS management) 13/2-005
-
9
Expectations from ReviewSpeaker: Steve Myers (CERN)
- 10
-
14:30
Discussion
- 11
-
14:50
Discussion
- 12
-
15:10
Discussion
-
13
Ion beam performance with and without IR3 upgradeIon performance reach without and with dispersion-suppressor collimators in IR3. Other ion limitations (IR2, ...). Possible impact from delay of IR3 work on IR2 upgrade of dispersion suppressors.Speaker: Giulia Bellodi (CERN)
-
15:30
Coffee Break
- 14
-
16:05
Discussion
-
15
Impedance without IR3 upgradeImpedance from tight collimation settings as achieved in MD. Will the beams be stable with impedance, taking into account stabilization from transverse damper and octupoles?Speaker: Nicolas Mounet (Ecole Polytechnique Federale de Lausanne (EPFL)-Unknown-Unknown)
-
16:25
Discussion
- 16
-
16:50
Discussion
- 17
-
17:10
Discussion
- 18
-
17:30
Discussion
-
9
-
17:40
Break
-
-
20:00
Review Dinner
-
-
-
Discussion of review committee with ATS and project management (closed) 13/2-005
-
-
12:30
Lunch
-
-
-