As anticipated during the EuroCirCol Meeting in Orsay (2015), the status of WP5 will be submitted at least once a year to a Technical Review Committee, with the aim of focussing the baseline assumptions, design methods and solutions, technical strategies including cost analysis, towards a credible design for a 16T demonstrator magnet for the FCC machine.
The review will be part of the FCC Review Program.
The 1st review will be held at CERN and is scheduled on 11th (start at 10h00) to 13th (end at 12h00) May 2016.
The charge includes comments and recommendations on:
The Review Panel is composed of:
The review will end with a close-out by the review Chair, in the form of a presentation. The review committee is asked to prepare a short report with their findings, comments and recommendations. The report is required within one month from the review.