Accelerator Technical and Operation Review
Main themes:
- 2007 machine operation review: main events & lessons learned
- Operation in 2008 at high intensity: radiation issues
- Situation of high radiation facilities (Isolde, nTof, Merit,…)
- MTTR and spare policy for the LHC injectors and experimental areas
- Safety issues
- Control issues for LHC injection (FE’s, software, performance)
Participants
    • Session 3 - Control Issues
      • 12
        The PS complex controls renovation project; scope and milestones
        Speaker: Simon Baird
        Abstract
        Slides
      • 13
        INCA:= Injector controls architecture; basic concept; milestones
        Speaker: Stephane Deghaye
        Abstract
      • 14
        FEC renovation; guidelines; time scale
        Speaker: Claude-Henri Sicard
        Abstract
        Slides
      • 15
        Maintenance concept of existing injector controls until replacement
        Speaker: Eugenia Hatziangeli
        Abstract
        Slides
      • 10:20
        Coffee break
      • 16
        Responsibility limits AB-CO towards AB equipment groups as agreed in CO3 and ABMB
        Speaker: Andrew Butterworth
        Abstract
        Slides
      • 17
        Responsibility limits AB-CO towards AT/TS equipment groups as agreed in AT-CO2 and GL meetings
        Speaker: Philippe Gayet
        Abstract
        Slides
      • 18
        Rapid Application Development Environment based on LabVIEW
        Speaker: Alessandro Raimondo
        Abstract
        Slides
    • Session 4 - MTTR & Spare Policy for the LHC<br>injectors & experimental areas: AT & IT Groups<br><br>

      <font face="Calibri" size="2" color="#000080">• Review per equipment group of the MTTR (Mean Time to Repair) and spare parts policy for the LHC backbone, the experimental areas and other facilities

      • Mitigation of long MTTR should be addressed (i.e. replacement of obsolete systems or systems where no spare parts are available)

      • Stand-by organization

      Contents of each presentation:

      • Main risks and impacts of systems

      • MTTR

      • Spares policy

      • Level and organization of service (piquet)

    • Session 5 - MTTR & Spare Parts Policy for the LHC injectors, experimental areas and other facilities: TS Groups & AB-ABP group

      <font face="Calibri" size="2" color="#000080">• Review per equipment group of the MTTR (Mean Time to Repair) and spare parts policy for the LHC backbone, the experimental areas and other facilities

      • Mitigation of long MTTR should be addressed (i.e. replacement of obsolete systems or systems where no spare parts are available)

      • Stand-by organization

      Contents of each presentation:

      • Main risks and impacts of systems

      • MTTR

      • Spares policy

      • Level and organization of service (piquet)

      slideshow template
    • Session 6 - MTTR & Spare Parts Policy for the LHC injectors, experimental areas and other facilities: AB Groups

      <font face="Calibri" size="2" color="#000080">• Review per equipment group of the MTTR (Mean Time to Repair) and spare parts policy for the LHC backbone, the experimental areas and other facilities

      • Mitigation of long MTTR should be addressed (i.e. replacement of obsolete systems or systems where no spare parts are available)

      • Stand-by organization

      Contents of each presentation:

      • Main risks and impacts of systems

      • MTTR

      • Spares policy

      • Level and organization of service (piquet)

      • 29
        MTTR, spare parts and stand-by policy for ATB equipments
        Speaker: Roberto Losito
        Abstract
        Slides
      • 30
        MTTR, spare parts and stand-by policy for BI equipments
        Speaker: Jocelyn Tan
        Abstract
        Slides
      • 31
        MTTR, spare parts and stand-by policy for BT equipments
        Speaker: Mr Jan Borburgh
        Abstract
        Slides
      • 15:30
        Coffee break (874 1-001)
      • 32
        MTTR, spare parts and stand-by policy for CO equipments
        Speaker: Marc Vanden Eynden
        Abstract
        Slides
      • 33
        MTTR, spare parts and stand-by policy for PO equipments
        Speaker: Christophe Mugnier
        Abstract
        Slides
      • 34
        MTTR, spare parts and stand-by policy for RF equipments
        Speaker: Carlo Rossi
        Abstract
        Slides
    • ATC/ABOC Days Summary CERN

      CERN

      Summing-up of the Accelerators Technical and Operation Review: ATC/ABOC days: 21-23 January 2008

      • 35
        Operation in 2007 and Outlook for 2008 AB Auditorium Prevessin

        AB Auditorium Prevessin

        CERN

        Speaker: Oliver Bruning
        Slides
      • 36
        Operation at high intensity of the CERN machines AB Auditorium Prevessin

        AB Auditorium Prevessin

        CERN

        Speaker: Doris Forkel-Wirth
        Slides
      • 37
        Control Issues AB Auditorium Prevessin

        AB Auditorium Prevessin

        CERN

        Speaker: Hermann Schmickler
        Slides
      • 38
        MTTR & Spare Policy for the LHC injectors, experimental areas and other facilities: AT & IT Groups AB Auditorium Prevessin

        AB Auditorium Prevessin

        CERN

        Speaker: Tim Smith
        Slides
      • 39
        MTTR & Spare Policy for the LHC injectors, experimental areas and other facilities: TS Groups & AB-ABP group AB Auditorium Prevessin

        AB Auditorium Prevessin

        CERN

        Speaker: Paolo Ciriani
        Slides
      • 40
        MTTR & Spare Policy for the LHC injectors, experimental areas and other facilities: AB Groups AB Auditorium Prevessin

        AB Auditorium Prevessin

        CERN

        Speaker: Steve Myers
        Slides